Field performance of a concrete pipe culvert installed using standard installations

  1. (PDF, 460 KB)
AuthorSearch for: ; Search for:
Conference1st Canadian Conference on Effective Design of Structures: 10 July 2005, Hamilton, Ontario
Pages591601; # of pages: 11
AbstractIn August 2000, a concrete pipe culvert of 1370 mm inside diameter was installed under a truck route in the former Regional Municipality of Ottawa-Carleton (now City of Ottawa) using the Standard Installations method. The project demonstrated two installation conditions, known as Type 2 and Type 3. In order to evaluate the pipe performance and verify the Standard Installations theory, two pipe sections were instrumented to evaluate the loading conditions and enable a comparison of the Standard Installations theory. The performance monitoring conducted over a three-year period showed good correlation with the Standard Installations theory. The measured performance of the pipe from the test site compared to the predicted performance for Standard Installations has resulted in some very informative findings on the interaction between pipe and soil, and provides the owners of infrastructure with design options for concrete pipe. This research offers a cost effective alternative to the current design method developed morethan seventy years ago.
Publication date
AffiliationNRC Institute for Research in Construction; National Research Council Canada
Peer reviewedYes
NRC number48187
NPARC number20378296
Export citationExport as RIS
Report a correctionReport a correction
Record identifier07a102ee-f7bb-41c9-8aba-bec79fd7cb0a
Record created2012-07-24
Record modified2016-05-09
Bookmark and share
  • Share this page with Facebook (Opens in a new window)
  • Share this page with Twitter (Opens in a new window)
  • Share this page with Google+ (Opens in a new window)
  • Share this page with Delicious (Opens in a new window)